Turn a volume estimate into an order
The calculator gives the geometric volume and weight-based bag equivalents. It does not automatically add an allowance for waste or uneven ground. Decide on an allowance for your project, then check the yield on the exact mix you plan to buy before rounding up to whole bags.
For a 10 ft by 10 ft pad at 4 inches thick, the base volume is 33.33 ft³, or about 1.23 yd³. An illustrative 10% allowance gives 36.67 ft³, or 1.36 yd³. The QUIKRETE Concrete Mix No. 1101 data sheet lists approximately 0.60 ft³ per 80 lb bag. At that yield, divide the unrounded ordering volume by 0.60 and round up: 62 bags. The 10% allowance is an example, not a requirement for every project.
To reproduce this order, choose Measured Area / Bag Order and enter 100 ft², 4 inches, 10% and 0.60 ft³ per bag. If you know the surface dimensions, calculate them in the Area Calculator and choose Use this area in Concrete. The measured-area mode assumes uniform thickness. Use the gravel calculator for a separate aggregate layer; concrete and gravel need their own depths and quantities.
How much concrete do I need?
Concrete is bought by volume, so every estimate comes down to one question: how many cubic yards (or cubic meters) of space will the wet mix fill? Measure the form, convert all dimensions to the same unit, apply the volume formula for the shape, and then add a margin for spillage, uneven subgrade and form bulge. Most contractors order 5 to 10 percent more than the calculated volume, because running short in the middle of a pour leaves a cold joint that weakens the finished slab.
Volume formulas by shape
Slabs, square footings and walls
This covers patios, driveways, shed bases, square pier footings and poured walls. Thickness is usually given in inches, so remember to divide by 12 before multiplying by feet.
Holes, columns and round footings
Use this for post holes, sonotube piers and round footings.
Circular slabs and tubes
A hollow tube or ring footing subtracts the inner circle from the outer one. Set the inner diameter to zero for a solid round slab.
Curb and gutter barriers
The curb is the raised lip, and the flag is the flat gutter pan in front of it. The curb portion runs the full height from the bottom of the flag to the top of the curb.
Stairs
Concrete steps are treated as a stack of blocks. Each of the first n − 1 steps is one run deep and as tall as the number of rises below its top. The top step is a platform that is as tall as all n rises combined.
Worked example
A 10 ft by 10 ft patio poured 4 inches thick has a volume of 10 × 10 × (4 ÷ 12) = 33.33 cubic feet. Divide by 27 to get 1.23 cubic yards, or about 0.94 cubic meters. At 133 lb per cubic foot of pre-mixed concrete it weighs about 4,433 lb, which is 4,433 ÷ 80 = 55.42, so you would buy 56 bags of 80 lb mix, or 4,433 ÷ 60 = 73.89, rounded up to 74 bags of 60 lb mix. With an illustrative 10 percent waste allowance, use the unrounded volume to get about 1.36 cubic yards.
Example bag yields: QUIKRETE Concrete Mix
| Bag size | Approximate published yield | Whole bags for 1 yd³ before allowance |
|---|---|---|
| 40 lb | 0.30 ft³ | 90 |
| 60 lb | 0.45 ft³ | 60 |
| 80 lb | 0.60 ft³ | 45 |
These example yields come from the QUIKRETE Concrete Mix product data sheet, checked November 6, 2026. They are approximate and specific to that product, not every concrete mix. Whole-bag quantities above use 27 ft³ per yd³ divided by the published yield, rounded up.
The calculator uses a separate weight-based method: it converts volume to weight at 133 lb per cubic foot (2,130 kg per cubic meter), then divides by the bag weight. Those weight-based equivalents can differ from a manufacturer’s published yield. Yields vary slightly by brand and mix design, so check the bag label.
Concrete weight
Bagged pre-mixed concrete weighs about 133 pounds per cubic foot, or roughly 3,590 pounds per cubic yard (about 2,130 kg per cubic meter). Normal-weight structural concrete from a ready-mix plant is denser, around 145 to 150 pounds per cubic foot. The weight matters when you plan how to haul bags, whether a trailer can carry the load, and how much a suspended slab adds to the structure below it.
Bags or ready-mix?
Bagged concrete makes sense for small jobs: fence posts, a few footings, or a small pad up to roughly half a cubic yard. Beyond about one cubic yard, mixing dozens of heavy bags by hand becomes slow and makes it hard to keep the pour consistent. Ready-mix trucks deliver a uniform batch, and many suppliers sell short loads for a fee. Get a quote both ways for anything between half a yard and two yards.
Tips for an accurate estimate
- Measure the actual form, not the plan. Forms often end up slightly larger than drawn.
- Check the subgrade. A low spot one inch deep across a 100 square foot slab adds more than 8 cubic feet.
- Round thickness up, not down, when the base is uneven.
- Order a little extra. Leftover concrete can fill a post hole or splash block, but a shortage cannot be fixed later without a seam.